How to Price a Change Order: Four Client Requests, Priced Line by Line

Knowing you should send a change order is easy. Knowing what number to put on it is the hard part. So here is a worked example with real arithmetic. The project is the same invented one from my scope of work example: a

Knowing you should send a change order is easy. Knowing what number to put on it is the hard part. So here is a worked example with real arithmetic.

The project is the same invented one from my scope of work example: a five-page website for a fictional bakery, Tidewell Bakery, already agreed and half built. The hourly rate is $50, which I picked for easy maths. Use your own.

The formula

  1. List the tasks, including the boring ones: setup, testing, deployment, and talking to the client.
  2. Estimate hours for each task.
  3. Add a buffer of 20 to 30 percent. Small changes hit unknowns more often than people expect.
  4. Multiply by your rate, then round to a clean number.
  5. State the effect on the delivery date, because time is part of the price.

The most common mistake is pricing only the part you can picture. "Add a gift card page" sounds like a page. It is actually a page, a payment flow, an email, testing and a policy question.

Request 1: "Can you show our Instagram feed on the homepage?"

Task Hours
Set up the feed plugin or embed and connect the account 1.5
Style it to match the site, mobile layout included 1.5
Test across browsers and phones 0.5
Client emails and one round of feedback 0.5
Subtotal 4.0
Buffer (25%) 1.0
Total 5.0 hours = $250

Timeline effect: about 1 working day.

Request 2: "Can we sell gift cards on the Catering page?"

This is the trap. It was written as one line and hides a lot.

Task Hours
Choose and configure a gift card plugin or service 2.0
Payment set-up and test transactions 3.0
Gift card page design and the emails buyers receive 2.5
Terms text and checkout wording (client supplies the terms) 0.5
Testing, including a refund and an expired card 1.5
Client communication and feedback 0.5
Subtotal 10.0
Buffer (30%, since payments always surprise) 3.0
Total 13.0 hours = $650

Timeline effect: about 4 working days, plus any time the client takes to decide on the terms.

Also say plainly: the payment provider charges its own fees, and the client needs their own account with it. That is not part of your price.

Request 3: "Could you make the logo bigger and the button green?"

Estimate: 20 minutes.

Do not quote this. Quoting $17 for a logo change looks petty, and the paperwork costs more than the work. Do it, and say so:

"Happy to do these two small tweaks as a courtesy. Just so we both keep track: this one is included, and anything bigger will get its own quote."

A courtesy is a decision you make out loud. A courtesy you never mention becomes the new baseline. One or two per project is generous. Ten is a pattern.

Request 4: "Can we have a Spanish version of the whole site?"

Task Hours
Multilingual set-up and language switcher 4.0
Duplicate and adapt the five pages and the menu structure 6.0
Pre-order form and emails in both languages 3.0
SEO set-up for the second language 2.0
Testing both versions 2.0
Client communication and review rounds 1.0
Subtotal 18.0
Buffer (25%) 4.5
Total 22.5 hours = $1,125

Timeline effect: about 8 working days.

What is not in the price: the Spanish text itself. The client supplies a translation, or pays a translator separately. If you skip this sentence, you will end up translating.

The quote as the client sees it

Here is Request 2 as a short change order. One page is enough.

CHANGE ORDER #2

Project:       Tidewell Bakery website
Requested:     Gift cards sold on the Catering page
Included:      Gift card plugin set-up, payment test, page design,
               buyer emails, testing (refund and expiry cases)
Not included:  Payment provider fees, the client's own provider account,
               the gift card terms text (supplied by client)
Cost:          $650 (13 hours at $50)
Timeline:      +4 working days from approval, delivery moves
               from 28 Nov to 4 Dec
All other terms of the original agreement stay the same.

Approved by: ________________    Date: ____________

Then the email that sends it:

Subject: Re: Gift cards

Hi Maria,

Happy to add gift cards. I have put the details in the attached change
order: $650, and it moves the launch date by four working days.

If you would like to go ahead, sign the form and I will start straight
away. If you would rather launch on the original date and add gift
cards afterwards, that works too.

Best,
Sam

Notice the last line. It gives the client a real choice, which makes "yes" easier and "no" painless.

Four pricing mistakes

  • Pricing the build and forgetting everything around it. Testing, deployment and communication are real hours.
  • Quoting a price without a date. A change that moves the launch is still a cost to the client, so say how much.
  • Using one buffer for every request. Payments, migrations and anything touching other people's systems deserve a bigger one than a plugin embed.
  • Hiding assumptions. If the price assumes the client provides the text or the account, write that down.

Quick reference

Type of request Typical handling
Tiny tweak, under half an hour Do it, label it as a courtesy
Small addition, a few hours Quote with a 20 to 25% buffer
Anything with payments, user data or a third party Quote with a 30% buffer and list assumptions
Big, vague request Offer a paid scoping hour first

This is an invented example with a made-up rate. Use your own numbers, and have a qualified lawyer review your agreement for larger projects.

Want the blank forms?

The change order form used above is free, along with three client emails, in a starter pack: https://kitvane.gumroad.com/l/free-starter-pack-for-freelance-developers

The full Freelance Developer Client Kit adds a proposal, a scope of work agreement, an onboarding checklist, a handover document, 17 client emails and an Excel invoice tracker: https://kitvane.gumroad.com/l/freelance-developer-client-kit

Disclosure: I created these templates and sell the kits under the KitVane name.

📰 Read the original article on Dev.to WebDev

Originally published by Dev.to WebDev. Aggregated on AIWithGhost for educational purposes — full credit and traffic to the original publisher.