How do you price a change request? New work + knock-on rework + timeline cost

To price a change request, add the hours for the new work to the hours of rework it causes in already-finished work, multiply by your rate, then add any timeline cost: (new_work_hours + knock_on_rework_hours) × hourly_ra

To price a change request, add the hours for the new work to the hours of rework it causes in already-finished work, multiply by your rate, then add any timeline cost: (new_work_hours + knock_on_rework_hours) × hourly_rate + timeline_cost. Start only after the client approves both the price and the new timeline.

Below: what goes into each part, a quick "rework sweep" so you stop missing the hidden hours, a hypothetical worked example, the same maths as spreadsheet cells, and the message that gets a clear yes.

Why the first number is usually wrong

The common pattern: mid-project, a client asks for a feature. "About four hours," you think, quote four hours, and get a fast yes. Then two pages you already built need layout changes to fit it, the QA you finished last week has to run again, the launch slips (and the final milestone payment with it), and you work a weekend to keep other clients on schedule.

You were paid for four hours. The change cost twelve, plus a delayed invoice. The fix isn't charging more for the sake of it. It's pricing the whole change, not just the visible part.

The formula, part by part

change_request_price = (new_work_hours + knock_on_rework_hours) * hourly_rate + timeline_cost

1. new_work_hours: the thing they asked for

Estimate it like any other task:

  • break it into steps (design, build, content, review, deploy) and estimate each one;
  • include one revision round for the new work, and say so in the request;
  • add the small stuff: the clarification call, project-management time, handover notes.

On a fixed fee? Estimate hours first, then convert to a price. It keeps the number grounded.

2. knock_on_rework_hours: what the change touches

This is the part that gets missed. Treat it like checking the blast radius of a code change: before you quote, walk every deliverable and ask "does this request change it?"

design      -> other pages or components that need adjusting for consistency
development -> refactoring, shared components, re-testing
content     -> copy that references the old structure, navigation, SEO metadata
qa/approval -> re-testing and re-approving work that was already signed off
marketing   -> creatives, landing pages, tracking when an offer or product changes

If the client already approved something, reworking it is chargeable. It's part of the cost of the change, not a favour. If you build software for clients, the same logic applies to sorting bugs from new features; scope creep in software development covers that triage.

3. timeline_cost: the cost of time

  • Rush effort: the client wants the change and the original deadline, which means overtime, contractors, or pushing other clients back. Many agencies add a percentage on top of the work cost. Pick one you'd be happy to defend.
  • Rescheduling: the next client's slot moves, or the team sits partly idle waiting on approvals.
  • Delayed payments: if your final invoice is tied to launch, a later launch means later cash. You don't have to bill for it, but you should know it, and you can adjust milestone timing in the change request.

Sometimes timeline_cost = 0 and the line is simply "This adds 3 business days; launch moves from [date] to [date]." Write it down anyway: the client is approving the delay as well as the price.

Worked example (hypothetical; all names and numbers are fictional)

A two-person web agency is building a 6-page site on a fixed fee, with an hourly rate of $85. Halfway through, the client asks for a pricing page with three plan cards and an FAQ, and still wants the original launch date.

New work

Task Hours
Design the pricing page in the existing style 4
Build the page and plan cards 5
FAQ section and content setup 2
One revision round on the new page 2
Clarification call and project management 1
Total 14

Knock-on rework

Task Hours
Update navigation and footer (already approved) 1.5
Adjust homepage "Plans" section to link to the new page 2
Re-run QA across affected pages 1.5
Total 5

Timeline: keeping the launch date means fitting about 19 extra hours into the existing schedule, by shifting another client's work and adding evening hours. They apply a 20% rush premium to the work cost. (That percentage is a hypothetical business choice, not a standard.)

work_cost     = (14 + 5) * $85 = 19 * $85 = $1,615
rush_premium  = 0.20 * $1,615             =   $323

option_A  keep launch date               = $1,938
option_B  launch moves 3 business days   = $1,615

naive quote (new page only) = 14 * $85    = $1,190

Quoting only the visible page would have left $425 of rework unpaid, and more once you count the rush.

The same thing as spreadsheet cells

With B1 = new work hours, B2 = rework hours, B3 = hourly rate, B4 = rush % (0 if the date can move):

Work cost:              =(B1+B2)*B3
Price, keep the date:   =(B1+B2)*B3*(1+B4)
Price, move the date:   =(B1+B2)*B3
Gap vs naive quote:     =(B1+B2)*B3 - B1*B3

Keep one row per change request and you also get a running record of how much each client's changes add up to, which is useful when the original package or retainer needs resizing.

Get the yes before the work starts

A well-priced change only protects you if the client agrees before you start:

1. check the request vs the scope -> included | extra | unclear
                                     (unclear: ask what "done" looks like first)
2. price it the same day          -> new work + rework + timeline
3. send the price + a short note  -> two options, A or B
4. start only after a written yes -> "approved, option B" is enough for most changes
5. log it                         -> price, new dates, updated invoice schedule

A fast reply with a clear price feels professional. A price that shows up a week later feels like a penalty. The note for step 3 can be this short:

Happy to add this. It's outside the current scope, so here's a quick change
request with the price and what it does to the timeline. Two options: keep the
launch date with a rush fee, or move launch by 3 days at the standard price.
Just reply with A or B.

For what the written offer itself should contain (the added work, what is not included, assumptions, price, timeline impact, and how the client approves), see how to quote additional work. For bigger changes, use a signature block, and make sure the person approving can actually approve the spend.

Do small changes need a formal change request?

Every extra needs a price and a yes before work starts, but not always a full form. For a small change, a one-line reply with the price and the client's "go ahead" does the same job.

And if you've been doing changes for free until now, you don't have to start charging for everything at once. Start with the next request: price it fully, offer a choice on timing, and get approval before you start.

Originally published at creepless.online. This version was drafted with AI assistance.