GS Group Breaks Ground on a 1.2 GW AI Data Center in Donghae in South Korea's Biggest AI Build Yet
South Korea's AI infrastructure promise is taking shape. On November 28, 2026, GS Group broke ground on a 1.2 GW AI data center in Donghae, Gangwon Province, the first gigawatt-scale project in the government's flagship
South Korea's AI infrastructure promise is taking shape. On November 28, 2026, GS Group broke ground on a 1.2 GW AI data center in Donghae, Gangwon Province, the first gigawatt-scale project in the government's flagship AI program. President Lee Jae-myung attended, a sign Seoul now views data centers that way.
Read the full article on Rohan Tech Official for the numbers and people behind it. Around 270 people gathered at the Bukpyeong No. 2 General Industrial Complex, among them GS Group Chairman Huh Tae-soo, Deputy Prime Minister and Science and ICT Minister Bae Kyung-hoon, Gangwon Governor Woo Sang-ho, Donghae Mayor Lee Jung-hak, and GS AI Infra CEO Do Hyun-soo.
The first gigawatt-scale build under Korea's flagship program
Within the government's "Three Mega-Projects for Korea's Great Leap", Donghae is the first gigawatt-scale AI data center to move into construction. Seoul unveiled the plan on June 29, 2026, and work began five months later.
Most data centers run in the tens of megawatts; a gigawatt is a different league. At 1.2 GW, this first phase alone would rank among the biggest AI data center builds anywhere. Donghae sits far from Seoul, a regional pick that fits the goal of spreading the build-out beyond the capital.
What phase one will actually contain
The main site covers roughly 80,000 pyeong, about 264,000 square meters, inside the Bukpyeong No. 2 complex. Three zones there hold 700 MW between them, and a separate 500 MW center elsewhere takes the first phase to its full 1.2 GW.
The phase is a group of centers, not one structure, finished and switched on in turn, so GS earns from the earliest ones while the rest are still being built. GS AI Infrastructure, a GS subsidiary, is building it, led by chief executive Do Hyun-soo.
The money and the timetable
Phase one carries a 15 trillion won investment plan, about $10.2 billion at current rates. Some outlets convert it to around $11.2 or $11.3 billion, so the won figure is the steadier one to follow.
In total, the plan runs to 2.4 GW across two 1.2 GW phases. Building all of it is estimated at around 30 trillion won. Yet the buildings are only part of the cost: add in GPUs, memory, and the rest of the computing hardware, and the total could climb to about 120 trillion won. Pricey shells, far pricier chips.
GS will fund roughly a fifth from equity and raise the rest through project finance. That split is standard at this scale, but it leaves the project depending on lenders who trust demand for AI computing will be there at opening.
The timetable is tight. The first 100 MW center should be finished in the second quarter of 2028, with the others to follow, and the entire 1.2 GW first phase is meant to be complete and running in 2029, roughly two and a half years on.
Why Donghae, and what comes next
In his welcoming address, Chairman Huh Tae-soo talked about the host city. He called Donghae famous for its sunrise and said GS aims to turn it into a destination where visitors come to see the AI industry's future. The message was plain: jobs and investment for Donghae, not only concrete and power lines.
Donghae's selection leaves a question: electricity. A 1.2 GW data center needs an enormous, steady supply, and the sources do not say where it will come from. GS Donghae Power, a GS Group coal-fired plant, stands nearby, but the sources stop short of saying the data center will draw power from it.
Donghae is one piece of a larger national build-out. With SK, GS, and Naver, the government wants 8.4 GW of AI data center capacity in a first phase, the three companies expected to invest about 550 trillion won, according to Aju Press on November 28.
Other countries answer differently. Canada has created a 1 billion dollar fund to widen access to AI computing, while US regulators have cleared orbital data centers, including the FCC clearing SpaceX's StarMind. Korea's answer is different: large land-based centers from its biggest industrial groups, with state backing.
The 8.4 GW target will turn on the same factors as Donghae's outcome: financing, power, equipment supply, and customers ready to rent the capacity. The ground is broken, the first center is due in the second quarter of 2028, and the wider program will be judged on what happens in Donghae next.
Originally published by Dev.to AI. Aggregated on AIWithGhost for educational purposes — full credit and traffic to the original publisher.